In wastewater treatment, rising inflows and tighter compliance requirements have traditionally meant one thing: build more capacity. But as climate change drives more intense and unpredictable weather, and capital investment faces greater scrutiny, utilities are increasingly looking for ways to get more from existing infrastructure.
At Belmont Wastewater Treatment Works, which serves around 100,000 residents around Lake Macquarie, heavy rainfall and rapid runoff can cause sharp increases in inflows. While the plant’s core processes perform reliably in dry weather, wet-weather events can push clarifiers towards their operating limits, increasing the risk of solids washout and placing pressure on downstream processes and regulatory compliance.
Historically, the solution would have been to construct additional clarifiers and flow-splitting infrastructure. At Belmont, however, this would have required approximately €5m ($5.2m) in capital expenditure, alongside months of construction at a live wastewater facility. The project team therefore explored whether the plant’s existing capacity could be used more effectively during storm events.
The decision to avoid €5m ($5.2m) in CAPEX
Hunter Water and its operating partner, Veolia, turned to digital optimisation as a potential alternative to major construction. The premise was straightforward: if process stress could be identified earlier and control strategies adjusted more quickly and precisely, could the plant manage wet-weather surges without exceeding performance limits?
Veolia’s Hubgrade Wastewater Plant (HWP) Performance platform was deployed to continuously analyse real-time operating conditions across the biological treatment process. Rather than replacing existing control systems, the platform worked alongside them, interpreting incoming data and optimising parameters including aeration, pumping and recirculation.
By analysing the interaction between different parts of the process, the system helped stabilise biological performance as inflows increased. This reduced stress on pumps and blowers and enabled the plant to absorb sudden hydraulic shocks without triggering wider operational issues.
The benefits were particularly evident during storm events. Clarifiers that had previously operated close to their limits achieved a measured 23% increase in solids-flux capacity under wet-weather conditions, reducing the risk of washout and helping to maintain compliance as inflows surged.
Dynamic aeration control also reduced daily energy consumption from approximately 2,070kWh to 1,440kWh, contributing to an overall site energy reduction of around 15%. Although energy savings were not the primary objective, they demonstrated how process intensity could be better matched to actual demand rather than worst-case conditions.
The capacity gains were supported by improved return activated sludge (RAS) control, which worked alongside Belmont’s existing stormwater-mode safeguards. These retain sludge in aeration tanks through intermittent aeration and mixing during high-flow events. Together, the measures expanded the plant’s effective operating envelope and supported the decision to defer major capital works.
For operators, the shift provided earlier visibility of emerging constraints and clearer guidance on how the process would respond. Rather than relying primarily on reactive intervention, teams could use predictive insights to manage changing conditions while retaining full control and the ability to revert to manual operation when required.
Beyond concrete solutions
Belmont’s experience demonstrates how digital optimisation can help utilities strengthen resilience without immediately resorting to major infrastructure expansion. By stabilising treatment performance during storm events, the plant was able to manage higher hydraulic loads without constructing new clarifiers or flow-splitting infrastructure, avoiding an estimated €5m ($5.2m) in capital expenditure.
The project also highlights a broader shift in how wastewater capacity can be understood. Rather than relying solely on physical headroom, utilities can improve effective capacity through deeper system insight and more adaptive operation. At Belmont, this approach helped maintain compliance, reduce operational pressure and lower energy consumption within the existing footprint.
As utilities face increasingly volatile inflow patterns and tighter regulatory expectations, the ability to adapt dynamically offers an alternative to building defensively. Digital optimisation will not eliminate the need for capital investment, but it can help utilities understand what their existing assets are capable of before committing to new infrastructure.
At Belmont, progress came not from physical expansion, but from using data to understand the system more deeply and respond more intelligently when conditions were at their most demanding. The project demonstrates that, in a world of increasingly constrained resources, some of the most effective solutions may come from unlocking more value from what already exists.